I thought plastic injection industry was a piece of cake. But let me tell you how serious this industry is after 4 months in this field. A plastic spoon as below will take roughly a week to complete! No kidding man!

In coming stock of raw material will require lead time of 2-3 days. Mould polish and refurbishment will take a day. Testing mould will take a day. Cycle time for this “minuscule” spoon is around a minute and so 5 days just finished like that. Production will run for 1 day or two to buffer for stock and then only you will have what all call it, a plastic spoon. Tough life uh?